By the MassBid Estimation team · Reviewed by a senior estimator with 10+ years of experience · Published · Updated
In short
In 40 general contractor estimates MassBid delivered, finishes (Division 09) were the largest trade at a median 18.1% of total trade cost, followed by general conditions at 10.7%, electrical at 8.0%, wood and plastics at 7.9%, openings (doors and windows) at 7.5%, HVAC at 7.2%, plumbing at 6.1% and concrete at 5.5%. All MEP trades together came to a median 26.5%, and 22.2% on the 18 whole-building jobs. By building system, those whole buildings split into interiors about 33%, MEP 22%, envelope 14%, general conditions 10% and structure 9%. Every job varies, so the ranges matter as much as the medians.
- Largest trade
- Finishes, Division 09: 18.1% median (middle half 13.2 to 31.2%)
- Electrical
- Division 26: 8.0% median (6.2 to 16.4%)
- HVAC / plumbing
- Division 23: 7.2% (4.9 to 11.3%); Division 22: 6.1% (3.9 to 12.5%)
- All MEP
- 26.5% median across jobs with MEP; 22.2% on whole buildings
- Concrete
- Division 03: 5.5% median (2.5 to 8.5%)
- General conditions
- Division 01: 10.7% median (8.1 to 13.8%)
- Data
- 40 GC estimates, 14 divisions priced per job (median), percentages only
Share of total trade cost by CSI division
Each row is the share of total trade cost a division took on the jobs where it was priced, and how often it was priced at all. A division that is missing on a job, such as concrete on an interior fit-out, is left out of that division's median rather than counted as zero.
| Division | Median share | Middle half of jobs | Priced on |
|---|---|---|---|
| 01 General requirements | 10.7% | 8.1 to 13.8% | 100% of jobs |
| 02 Existing conditions and demolition | 2.9% | 1.3 to 7.2% | 78% |
| 03 Concrete | 5.5% | 2.5 to 8.5% | 65% |
| 04 Masonry | 1.5% | 0.6 to 3.2% | 45% |
| 05 Metals | 1.5% | 0.4 to 4.3% | 68% |
| 06 Wood, plastics and composites | 7.9% | 4.0 to 13.3% | 95% |
| 07 Thermal and moisture protection | 4.8% | 2.1 to 8.2% | 82% |
| 08 Openings | 7.5% | 4.2 to 10.4% | 95% |
| 09 Finishes | 18.1% | 13.2 to 31.2% | 95% |
| 10 Specialties | 1.0% | 0.5 to 2.7% | 68% |
| 11 Equipment | 1.2% | 0.7 to 2.4% | 65% |
| 12 Furnishings | 1.3% | 0.7 to 2.5% | 82% |
| 22 Plumbing | 6.1% | 3.9 to 12.5% | 68% |
| 23 HVAC | 7.2% | 4.9 to 11.3% | 68% |
| 26 Electrical | 8.0% | 6.2 to 16.4% | 75% |
| 27 Communications | 1.1% | 0.5 to 3.6% | 48% |
| 28 Electronic safety and security | 0.6% | 0.3 to 0.9% | 45% |
| 31 Earthwork | 1.2% | 1.0 to 1.6% | 28% |
| 33 Utilities | 2.5% | 0.8 to 6.8% | 32% |
Whole buildings: the split by building system
Eighteen of the jobs priced a complete building: concrete, envelope, plumbing, HVAC and electrical were all in the estimate. About half were houses and small multifamily buildings; the rest included a hotel, a restaurant, a childcare center, a visitor center, an aircraft hangar and a mixed-use development. Grouped by building system:
| Building system | Divisions | Median share | Middle half of jobs |
|---|---|---|---|
| Interiors and finishes | 06, 09, 10, 11, 12 | 33.0% | 23.1 to 44.2% |
| MEP | 21 to 28 | 22.2% | 16.2 to 35.5% |
| Envelope | 07, 08 | 14.0% | 9.7 to 18.1% |
| General conditions | 01 | 10.1% | 7.7 to 11.7% |
| Structure | 03, 04, 05 | 9.2% | 7.4 to 15.1% |
| Site work and utilities | 31, 32, 33 | 1.9% | 0 to 5.9% |
| Demolition | 02 | 0.4% | 0 to 2.5% |
Two things surprise people. First, the structure is usually the smaller part of the cost: on these low-rise buildings, concrete, masonry and steel together took a median 9.2%, less than a third of what the interiors took. Second, the systems you see least, MEP, take more than a fifth of the money, and on equipment-heavy buildings well over a third.
Quick answers: what percentage of construction cost is…
- What percentage of construction cost is electrical?
- A median 8.0% of total trade cost across 30 jobs that priced electrical, with the middle half between 6.2% and 16.4%. It rises with lighting, power-hungry equipment and low-voltage systems.
- What percentage of construction cost is plumbing?
- A median 6.1% across 27 jobs (middle half 3.9 to 12.5%). Restaurants, healthcare and multifamily, with many fixtures per square foot, sit at the top.
- What percentage of construction cost is HVAC?
- A median 7.2% across 27 jobs (middle half 4.9 to 11.3%).
- What percentage of construction cost is MEP in total?
- A median 26.5% of total trade cost on the 25 jobs that priced plumbing, HVAC and electrical, and 22.2% on the 18 whole-building jobs. Laboratory, hospital and data-center work runs far higher than these buildings.
- What percentage of construction cost is finishes?
- A median 18.1% across 38 jobs (middle half 13.2 to 31.2%): drywall, ceilings, flooring, tile and paint. On renovation and tenant-improvement jobs, finishes often take a third or more.
- What percentage of construction cost is concrete?
- A median 5.5% across 26 jobs that priced concrete (middle half 2.5 to 8.5%). It climbs on buildings with heavy foundations and on concrete-framed structures.
- What percentage of construction cost is roofing, insulation and waterproofing?
- Division 07 took a median 4.8% across 33 jobs (middle half 2.1 to 8.2%).
- What percentage of construction cost is doors, frames, hardware and windows?
- Division 08 took a median 7.5% across 38 jobs (middle half 4.2 to 10.4%).
- What percentage of construction cost is general conditions?
- A median 10.7% across all 40 jobs, falling from 13.8% on jobs under $500,000 to 7.8% over $2 million.
The general conditions figures are broken down further in general conditions in construction.
Why your building's split will differ
- New construction or renovation. On the renovation and tenant-improvement jobs in the data, finishes took a median of about 38% of trade cost, against about 18% on the rest, because there is little structure or site work to price.
- Building type. Restaurants and healthcare carry more plumbing and equipment; warehouses carry more concrete and steel and very little finish; houses carry more wood framing and millwork.
- What the owner buys separately. Owner-furnished equipment, separate site contracts and owner-paid permits all lower the share of the divisions they touch.
- Structure type. A concrete or steel frame moves several points of cost into Divisions 03 and 05 compared with wood or load-bearing masonry.
- Job size. Fixed costs, general conditions above all, take a bigger share on small jobs.
- Location. Labor-heavy trades shift more than material-heavy ones between high- and low-wage markets, so the split moves even when the building does not.
How estimators use a cost breakdown
- Checking a conceptual budget. Split the budget by system and ask whether each part can buy what the design shows. A tight MEP share on a restaurant is a warning.
- Spotting a missing scope. If a division in a bid is far below its usual range, look for something left out, such as a missing sheet or an exclusion. In our study of bid sets, more than half had at least one gap or conflict; see the construction drawing errors study.
- Leveling subcontractor bids. A plumbing bid at 2% of a medical office's trade cost probably does not include what you think it does.
- Explaining a number to an owner. Owners understand shares faster than line items: "a fifth of this budget is the building's systems" lands better than a 40-page estimate.
Shares are for checking, never for pricing. A bid needs measured quantities and local prices. If you organize budgets by building element instead of trade, see UniFormat vs MasterFormat.
Budget split calculator
Enter a total trade cost or a construction budget before markups. The tool splits it by building system at the median shares of the 18 whole-building estimates, with the range of the middle half of jobs.
Budget split by building system
| System | Typical | Middle half of jobs |
|---|---|---|
| Interiors and finishesDivisions 06, 09, 10, 11, 12 | $726,87236.3% | $462,000 to $884,000 |
| MEP (plumbing, HVAC, electrical, fire, low voltage)Divisions 21 to 28 | $488,98724.4% | $324,000 to $710,000 |
| Envelope (roofing, insulation, doors, windows)Divisions 07, 08 | $308,37015.4% | $194,000 to $362,000 |
| General conditionsDivisions 01 | $222,46711.1% | $154,000 to $234,000 |
| Structure (concrete, masonry, steel)Divisions 03, 04, 05 | $202,64310.1% | $148,000 to $302,000 |
| Site work and utilitiesDivisions 31, 32, 33 | $41,8502.1% | $0 to $118,000 |
| Demolition and existing conditionsDivisions 02 | $8,8110.4% | $0 to $50,000 |
Typical = each system's median share, scaled so the column adds to your budget. The range is the 25th to 75th percentile of that system's share in 18 whole-building estimates. A conceptual split for checking a budget or spotting a missing scope, not an estimate of your building.
How the data was collected
- Source: the division summaries of general contractor estimates MassBid Estimation prepared for US projects, read in November 2026.
- Included: estimates with general conditions priced and at least eight CSI divisions priced, so each job is a multi-trade building, not one trade. Each project is counted once; revised versions are not counted again. Bridge and heavy civil jobs are excluded.
- Result: 40 jobs from about $45,000 to about $34 million in trade cost, with a median of 14 divisions priced per job. Eighteen priced a whole building.
- Measure: each division's trade cost divided by the total trade cost of all divisions, before overhead and profit, insurance, contingency and tax. Medians and 25th to 75th percentiles are reported.
- Published: percentages only. No client, project, address or price is published.
- Limits: the jobs are mostly low-rise commercial, residential and interior work. High-rise, hospital, laboratory and industrial process buildings are not represented and will split differently.
To cite: MassBid Estimation, "Construction cost breakdown by trade", November 2026, massbidestimation.com/guides/construction-cost-breakdown-by-trade.
Getting the real breakdown for your project
Every MassBid estimate is organized by CSI division, with each division's total and share on the summary, so you can compare it with these ranges straight away. See general contractor estimating, MEP estimating, the CSI divisions list, or send the drawings for a free quote.
Common questions
In 40 general contractor estimates MassBid delivered, the median shares of total trade cost were: finishes 18.1%, general conditions 10.7%, electrical 8.0%, wood and plastics 7.9%, doors and windows 7.5%, HVAC 7.2%, plumbing 6.1%, concrete 5.5% and roofing and insulation 4.8%, with smaller shares for demolition, masonry, metals, specialties, equipment and furnishings.
A median 8.0% of total trade cost across 30 MassBid estimates that priced electrical, with the middle half of jobs between 6.2% and 16.4%.
A median 26.5% of total trade cost across 25 jobs that priced plumbing, HVAC and electrical, and 22.2% on 18 whole-building jobs, in MassBid's data. Hospitals, laboratories and data centers run much higher.
A median 6.1% of total trade cost across 27 MassBid estimates (middle half 3.9 to 12.5%). Buildings with many fixtures, such as restaurants and multifamily, are at the high end.
A median 7.2% of total trade cost across 27 MassBid estimates, with the middle half of jobs between 4.9% and 11.3%.
A median 18.1% across 38 MassBid estimates, the largest single trade. On renovation and tenant-improvement work, finishes often take a third or more of the trade cost.
A median 5.5% of total trade cost across 26 MassBid estimates that priced concrete, with the middle half between 2.5% and 8.5%.
On 18 whole-building MassBid estimates, concrete, masonry and steel together took a median 9.2% of trade cost, while interiors and finishes took 33%, MEP 22% and the envelope 14%.
From the division summaries of 40 general contractor estimates MassBid Estimation prepared for US projects, each counted once, measured as each division's share of total trade cost before markups. Only percentages are published.
