General conditions in construction: what percentage to carry, with a checklist and data from 40 real estimates

What general conditions are, the two meanings of the term, what share of trade cost 40 real GC estimates carry by job size, where the money goes, a 60-item checklist with OSHA counts, and a calculator.

By the MassBid Estimation team · Reviewed by a senior estimator with 10+ years of experience · Published · Updated

In short

General conditions are the costs of running the job site that belong to no single trade: supervision, temporary facilities and utilities, mobilization, permits, cleaning, submittals and access equipment. They are not home-office overhead and not profit. Across 40 general contractor estimates MassBid delivered, general conditions came to a median 10.7% of total trade cost, with the middle half of jobs between 8.1% and 13.8%. The share falls as jobs grow: a median 13.8% under $500,000, 10.4% from $500,000 to $2 million and 7.8% over $2 million. Supervision is the biggest part, nearly 40% of the general conditions dollars.

Typical share
10.7% of trade cost (median, 40 GC estimates); middle half 8.1 to 13.8%
Under $500,000
13.8% median; middle half 11.9 to 18.9%
$500,000 to $2 million
10.4% median; middle half 8.1 to 12.0%
Over $2 million
7.8% median; middle half 5.1 to 10.5%
Biggest part
Supervision and project management: about 38% of general conditions
What drives it
Duration first, then site logistics, then the Division 01 specification
Not included
Home-office overhead, profit, insurance, bonds, contingency, tax

General conditions means two different things

Before arguing about a percentage, settle which general conditions you mean. The same two words name a contract document and a cost, and people talk past each other all the time.

The two meanings of general conditions in construction
MeaningWhat it isWhere you see it
The contract documentThe standard terms that govern the contract: the parties' duties, payment, changes, time, claims, insurance, terminationAIA A201 General Conditions of the Contract for Construction; ConsensusDocs 200; EJCDC C-700; federal FAR clauses
The costThe job-site costs of managing and supporting the work that no single trade carriesA line or a division in the estimate, the schedule of values and every pay application

The two are linked: the contract general conditions, plus Division 01 of the specification, decide which job-site costs the general contractor must carry. Everything below is about the cost.

General conditions vs general requirements, overhead, profit and contingency

Most disputes over a general contractor's bid come from six allowances being lumped together. Each one belongs on its own line:

General conditions compared with general requirements, overhead, profit and contingency
AllowanceWhat it coversHow it is priced
General conditionsRunning this job site: superintendent, project manager's time on the job, trailer, toilets, temporary power, fencing, dumpsters, cleaningBuilt from the schedule: monthly costs × duration, plus one-time items
General requirements (Division 01)The specification's administrative and temporary-facility rules for the whole project; in many estimates the same costs as general conditionsRead from Division 01 and priced into the general conditions lines
Overhead (home office)Running the company: office rent, estimators, accounting, executives, softwareA percentage on the whole job, after general conditions
ProfitThe contractor's return for riskA percentage, after overhead
ContingencyUnknowns in scope, design or priceA percentage or lump sum on the whole estimate
Insurance and bondsGeneral liability, builder's risk, payment and performance bondsPercentages or rates on the contract value, usually separate lines

On cost-plus and construction-manager contracts with a guaranteed maximum price, owners often split the first two: general conditions for the contractor's staff and site facilities, often as a fixed fee, and general requirements for the other Division 01 costs, reimbursed at cost. Read how your contract defines each before you price either. If it is silent, say in your bid which items you carry where.

What share of trade cost 40 real estimates carry

Published ranges for general conditions run from 5 to 15 percent and rarely say where the figure came from. To give real numbers, we read the division summaries of the general contractor estimates we have delivered and kept every job that met three rules: general conditions were priced as their own lines; at least eight divisions were priced, so the job was a whole building and not one trade; and each project was counted once, even when it was revised. Forty jobs qualified, from about $45,000 to about $34 million in trade cost, including retail, restaurant, office, healthcare, school, hotel, multifamily, residential and government work.

General conditions as a share of total trade cost in 40 MassBid general contractor estimates, by job size
Total trade costJobsMedianMiddle half of jobsLowest to highest
All jobs4010.7%8.1 to 13.8%2.1 to 26.4%
Under $500,0001413.8%11.9 to 18.9%6.5 to 26.4%
$500,000 to $2 million1910.4%8.1 to 12.0%2.1 to 20.7%
Over $2 million77.8%5.1 to 10.5%2.6 to 11.6%
Share = general conditions ÷ total trade cost of all divisions, general conditions included, before overhead and profit, insurance, contingency and tax. Middle half = 25th to 75th percentile. Percentages only; no project names or prices are published.

Three things in the data match what experienced estimators see on every bid:

  • Small jobs carry a bigger share. A superintendent, a trailer, a dumpster, permits and mobilization cost much the same whether the building is 2,000 or 20,000 square feet, so on a small job they are a bigger slice. A 13 to 19 percent figure on a $300,000 tenant improvement is not padding.
  • The share keeps falling on big jobs, but the dollars do not. On large jobs the staff grows, yet the trade cost grows faster, so general conditions settle near 8 percent or a little under.
  • The spread is wide at every size. The jobs at the top had long durations for their size, phased or occupied work, or heavy temporary protection; the jobs at the bottom were short, or had the owner carry permits and site facilities. That spread is why the percentage is a check, never the estimate.

Where the general conditions money goes

In 33 of the same jobs the general conditions were broken into priced lines, so we could see where the money sits. The medians:

Median share of general conditions dollars by category in 33 MassBid general contractor estimates
CategoryMedian share of general conditionsMiddle half of jobs
Supervision and project management37.5%31.6 to 45.2%
Mobilization and demobilization28.1%24.3 to 33.3%
Temporary facilities and controls11.5%8.5 to 16.3%
Submittals and documentation4.5%1.6 to 5.6%
Final cleaning4.4%2.4 to 9.0%
Permits, fees and inspections3.8%0.3 to 7.2%
Scaffolding and access3.6%2.4 to 5.2%
Medians of each category's share on each job, so they do not add to exactly 100%. Permits vary the most because owners often pay them directly.

The lesson is simple: general conditions are mostly people and time. Supervision and the costs that run by the month are where an estimate is won or lost. If the duration in your general conditions does not match the schedule you are promising, nothing else on the sheet will save the number.

General conditions checklist: 60+ items to price or rule out

Use this to make sure nothing is left out. Not every job needs every item; the point is to decide each one on purpose. Time-based items are priced per month × duration, one-time items as a lump sum, and quantity items by count.

General conditions checklist by group, with how each item is usually priced
GroupItemsUsually priced
Project staffSuperintendent; assistant superintendent; project manager's share of time; project engineer; field clerk; safety manager; quality control manager; scheduler; travel, per diem and lodging for out-of-town staff; staff vehicles and fuel; phones and laptopsPer month × duration
Field officeJob trailer or leased space; delivery and set-up; furniture; plan table; copier and printing; internet; office supplies; storage containers; owner and architect trailer if the specification requires onePer month, plus one-time set-up and removal
Temporary utilitiesTemporary power service and distribution; temporary lighting; temporary water; temporary heat; cooling and dehumidification for finishes; fuel; utility company connection feesPer month, plus one-time connections
Sanitation and welfarePortable toilets (OSHA count, below); hand-wash stations; servicing; drinking water; first-aid suppliesPer month × units
Site access and securityPerimeter fence and gates; barricades; traffic control and flaggers; construction entrance; haul road upkeep; staff parking; security guard or camerasPer month, plus install and removal
Protection and enclosuresTemporary partitions and dust barriers in occupied buildings; floor and finish protection; weather enclosures; winter protection; protection of existing work and adjacent propertyLump sum or per area
SafetyFire extinguishers (OSHA count, below); guardrails and fall protection; safety signage; personal protective equipment for staff; safety meetings; site-specific safety planLump sum, plus per month
Equipment and accessScaffolding; aerial lifts shared by trades; forklift or telehandler; hoist; crane days for the general contractor's own picks; small toolsPer month or per day
MobilizationMoving staff, equipment and facilities on and off site; layout and survey control; pre-construction photos and condition surveyLump sum, on and off
Permits, fees and testingBuilding permit if not paid by the owner; trade permits not carried by subcontractors; plan review; impact fees; special inspections and testing if assigned to the contractorLump sum or by allowance
DocumentationSubmittals and shop drawing management; RFIs; meeting minutes; schedule updates; progress photos; record drawings; operation and maintenance manuals; warranties; training; closeoutLump sum or per month
Cleaning and wasteDaily and weekly cleanup labor; dumpsters and hauling; recycling reports if the specification asks; window washing; final cleaning; punch list laborPer month for dumpsters and labor; lump sum or per square foot for final cleaning
Project identificationProject sign; temporary signage; wayfinding for the publicLump sum
Usually NOT herePayment and performance bonds; general liability and builder's risk insurance; home-office overhead; profit; contingency; sales taxSeparate lines after general conditions

Two quantity rules from OSHA that belong in every general conditions take-off:

OSHA quantity rules for portable toilets and fire extinguishers on construction sites
ItemOSHA ruleSource
Toilets20 workers or fewer: 1 toilet. 20 or more: 1 toilet seat and 1 urinal per 40 workers. 200 or more: 1 toilet seat and 1 urinal per 50 workers.29 CFR 1926.51(c), Table D-1
Fire extinguishersAt least one 2A-rated extinguisher for each 3,000 sq ft of the building, with no more than 100 ft of travel to reach one; one on each floor of a multistory building, by the stairway29 CFR 1926.150(c)(1)
Count workers at the peak of the manpower curve, not the average.

How to estimate general conditions, step by step

  • Start from the schedule, not a percentage. Set the construction duration and the staffing for each phase: when the superintendent starts, when the project manager is full time, when the assistant drops off.
  • Read Division 01 line by line. Sections such as 01 31 00 Project Management and Coordination, 01 33 00 Submittal Procedures, 01 45 00 Quality Control, 01 50 00 Temporary Facilities and Controls, 01 74 00 Cleaning and Waste Management and 01 77 00 Closeout Procedures tell you what the owner expects you to provide. Mark each requirement priced or excluded.
  • Sort every item into time, one-time or quantity. Time items are monthly cost × months on site; one-time items are lump sums; quantity items, such as toilets and extinguishers, are counts from the rules above.
  • Check who carries what. Dumpsters, final cleaning, scaffolding, hoisting, temporary power and permits are the items most often carried twice (by you and a subcontractor) or not at all. Settle it against each subcontractor's scope.
  • Price at local rates. Staff costs with burden, rental rates and haul charges vary by market. Use your own payroll and current local quotes.
  • Check the total against the percentage. Compare your build-up with the range for the job's size in the table above, or in the calculator below. If you are far outside it, find the reason: a long duration, phasing or an owner-furnished item. Do not just move the number.

General conditions calculator

Enter the trade cost of every other division and the duration. The calculator places the job in its size band and shows the typical general conditions and the range from our 40 estimates, split by category, plus the monthly figure to test against your real staff costs.

General conditions check

Job size band
$500,000 to $2 million (19 jobs)
Typical general conditions
$98,661 (10.4%)
Middle half of our jobs
$74,918 to $115,909
Per month of duration
$12,333

The percentage is general conditions as a share of total trade cost, before overhead, profit, insurance, contingency and tax, so the dollar figure is direct cost × % ÷ (100 − %). Use it to check a priced general conditions build-up, not to replace one: if the monthly figure will not cover your superintendent, the build-up is short.

Typical general conditions dollars split by category for the figure above
CategoryShareOf the typical figure
Supervision and project management40.1%$39,612
Mobilization and demobilization30.1%$29,683
Temporary facilities and controls12.3%$12,148
Submittals and documentation4.8%$4,753
Final cleaning4.7%$4,648
Permits, fees and inspections4.1%$4,014
Scaffolding and access3.9%$3,803

What gets missed in general conditions

On the bids we price and review, the same omissions come up again and again. Most of them are time, or work at the edge of two scopes:

  • Duration that does not match the schedule. Six months of supervision on an eight-month job is the most expensive mistake on this list.
  • Pre-construction and closeout time. The project manager works before mobilization and after substantial completion; punch list and closeout can add a month or more.
  • Temporary heat, enclosures and dehumidification in winter, and drying time before flooring and paint.
  • Protection in occupied buildings: dust walls, negative air, after-hours work and phasing that sets up the same facilities twice.
  • Hoisting and material handling on multistory work that no subcontractor carried.
  • Dumpsters assumed in the demolition subcontract, and final cleaning assumed in each trade's scope. Both are usually excluded there.
  • Specified extras in Division 01: an owner's trailer, a full-time quality control manager, specific progress photos, a recycling report, extra O&M copies or owner training.
  • Traffic control and police details on city streets, and street or sidewalk permits.
  • Travel and lodging for out-of-town staff.

How we price general conditions in our estimates

On every general contractor estimate we build general conditions as priced lines from your duration and the Division 01 specification, at the project's local rates, and we show them separately from overhead, profit, insurance and contingency so you can change any of them. If you have your own general conditions template or staff rates, we use yours. See how to read a construction estimate, the CSI divisions list for where each item sits, or send the drawings for a free quote.

Common questions

The costs of running the job site that belong to no single trade: supervision, temporary facilities and utilities, mobilization, permits, cleaning, submittals and shared access equipment. The term also names the contract document that sets the standard terms, such as AIA A201.

Across 40 general contractor estimates MassBid delivered, general conditions were a median 10.7% of total trade cost, with the middle half of jobs between 8.1% and 13.8%. Jobs under $500,000 had a median of 13.8%, jobs from $500,000 to $2 million 10.4%, and jobs over $2 million 7.8%.

Project staff (superintendent, project manager time, project engineer), the field office, temporary utilities, toilets, fencing and site security, protection, safety, shared equipment such as scaffolding and lifts, mobilization, permits not paid by the owner, submittals and closeout documents, dumpsters, cleanup and final cleaning.

General requirements is Division 01 of the specification: the administrative and temporary-facility rules for the whole project. General conditions is the cost of meeting them and running the site. In many estimates they are the same lines. On cost-plus and GMP contracts, owners often split them: general conditions for the contractor's staff and site facilities, general requirements for the other Division 01 costs.

No. General conditions are job-site costs of this project. Overhead is the cost of running the company, such as office rent, estimating and accounting, and is added as a percentage on top. Profit, insurance, bonds and contingency are separate again.

Build them from the schedule: monthly costs such as staff, trailer, toilets, temporary utilities and dumpsters multiplied by the months on site, plus one-time items such as mobilization, permits, signage and final cleaning, plus counted items such as toilets and fire extinguishers. Then check the total against a percentage range for the job's size.

Many site costs, such as a superintendent, a trailer, a dumpster, permits and mobilization, cost about the same on a small job as on a larger one, so they are a bigger share of a small trade cost. In MassBid's data the median falls from 13.8% under $500,000 to 7.8% over $2 million.

Supervision and project management. In 33 MassBid general contractor estimates with itemized general conditions, it was a median 37.5% of the general conditions dollars, followed by mobilization at about 28% and temporary facilities at about 12%.

Under OSHA 29 CFR 1926.51 Table D-1: one toilet for 20 workers or fewer; one toilet seat and one urinal per 40 workers for 20 or more; and one toilet seat and one urinal per 50 workers for 200 or more.

Usually not. Payment and performance bonds, general liability and builder's risk insurance are normally separate lines priced on the contract value, after general conditions. Some contracts require them inside general conditions, so check the definitions.