In short

Construction drawing abbreviations are short forms used on plans, sections, schedules and notes. The most common are TYP (typical: applies everywhere the condition repeats), UNO (unless noted otherwise), AFF (above finished floor), O.C. (on center), NIC (not in contract), NTS (not to scale), SIM (similar), EQ (equal) and T/ and B/ (top of and bottom of). Several mean different things on different sheets, such as EF (each face on structural, exhaust fan on mechanical) and RCP (reflected ceiling plan or reinforced concrete pipe), so the set's own abbreviation legend, usually on the first general or architectural sheet, always wins.

Where the legend is
First general (G) or architectural (A) sheet, sometimes on each discipline's first sheet
Most used
TYP, UNO, AFF, O.C., SIM, EQ, NTS, NIC, T/ and B/
UNO (U.N.O., UON)
Unless noted otherwise: the default for the sheet unless a note says different
Changes the price
NIC, FBO, OFCI, ALT, EXIST, EW, EF, T&B, TYP
Mean two things
EF, EA, RCP, PT, SD, CB, WP, W, WC, FD
Rebar callouts
#5 @ 12" O.C. EW T&B = #5 bars, 12 in. apart, both ways, top and bottom
In this list
271 abbreviations across seven disciplines

Search the abbreviation list

Type an abbreviation or a word, or filter by discipline. Each entry is filed under the discipline whose sheets use it most; where the same letters mean something else on another discipline's sheets, the note says so.

Abbreviation lookup

271 of 271 abbreviations

Construction drawing abbreviations, their meanings and the discipline whose sheets they appear on
Abbr.Meaning
(N)NewGeneral
(R)Remove or relocateCheck the legend; firms use it both waysGeneral
@AtSpacing, as in #5 @ 12" O.C.General
A or AMPAmpereElectrical
ABAnchor boltStructural
ACAsphalt concreteAlso air conditioning on mechanical sheetsCivil and site
ACPAcoustical ceiling panelArchitectural
ACTAcoustical ceiling tileArchitectural
ADAAmericans with Disabilities ActArchitectural
AFCIArc-fault circuit interrupterElectrical
AFFAbove finished floorMounting heights of outlets, switches, fixtures and accessoriesGeneral
AFGAbove finished gradeGeneral
AHUAir handling unitMechanical
AICAmpere interrupting capacityElectrical
ALTAlternateA bid alternate is priced separately from the base bidGeneral
ALUMAluminumArchitectural
APPROXApproximateGeneral
ARCHArchitect or architecturalGeneral
ASIArchitect's supplemental instructionGeneral
ATSAutomatic transfer switchElectrical
B/Bottom ofAs in B/FTG, bottom of footingStructural
BCBack of curb, or bottom of curbCivil and site
BDBoardArchitectural
BFP or BFVBackflow preventerPlumbing and fire
BLDGBuildingGeneral
BMBenchmarkCivil and site
BMPBest management practiceStormwater and erosion controlCivil and site
BODBasis of designThe named product others must equalGeneral
BOFBottom of footingStructural
BOTBottomStructural
BRGBearingStructural
BRKBrickArchitectural
BTU or BTUHBritish thermal units (per hour)Mechanical
BW / TWBottom of wall / top of wallRetaining wall gradesCivil and site
CConduitElectrical
C&GCurb and gutterCivil and site
CBCatch basinCivil and site
CBCircuit breakerCatch basin on civil sheetsElectrical
CDCeiling diffuserMechanical
CFMCubic feet per minuteMechanical
CICast ironPlumbing and fire
CIPCast-in-place concreteStructural
CJControl jointArchitectural
CJPComplete joint penetration weldStructural
CKTCircuitElectrical
CL or ℄CenterlineGeneral
CLGCeilingArchitectural
CLRClear or clearanceGeneral
CMPCorrugated metal pipeCivil and site
CMUConcrete masonry unitConcrete blockArchitectural
COCleanoutPlumbing and fire
COLColumnArchitectural
CONCConcreteStructural
CONTContinuousGeneral
CONTRContractorGeneral
CPTCarpetArchitectural
CTCeramic tileArchitectural
CUHCabinet unit heaterMechanical
CWCold waterPlumbing and fire
CWS / CWRChilled water supply / returnMechanical
DCVADouble check valve assemblyPlumbing and fire
DET or DTLDetailGeneral
DFDrinking fountainArchitectural
DIA or ØDiameterGeneral
DIMDimensionGeneral
DIPDuctile iron pipeCivil and site
DLDead loadStructural
DNDownGeneral
DSDownspoutArchitectural
DWGDrawingGeneral
DWLDowelStructural
DWVDrain, waste and ventPlumbing and fire
DXDirect expansionMechanical
EAEachGeneral
EAExhaust airOn general notes EA means eachMechanical
EFEach faceRebar on both faces: double the bar countStructural
EFExhaust fanOn structural sheets EF means each faceMechanical
EGExisting gradeCivil and site
EIFSExterior insulation and finish systemArchitectural
EJExpansion jointArchitectural
EL or ELEVElevationA height above a datum, or an elevation viewGeneral
EMEmergencyEmergency lighting and circuitsElectrical
EMTElectrical metallic tubingElectrical
EOPEdge of pavementCivil and site
EPDMEthylene propylene diene monomer roofingArchitectural
EQEqualSpace equallyGeneral
ERVEnergy recovery ventilatorMechanical
EWEach wayBars both directions: take off bothStructural
EWCElectric water coolerPlumbing and fire
EXIST or (E)ExistingExisting work is usually not in the new-work takeoffGeneral
EXTExteriorArchitectural
FACPFire alarm control panelElectrical
FBOFurnished by othersExcluded from your material priceGeneral
FCOFloor cleanoutPlumbing and fire
FCUFan coil unitMechanical
FDFire damper, or floor drainFloor drain on plumbing sheetsMechanical
FDCFire department connectionPlumbing and fire
FDNFoundationStructural
FEFire extinguisherArchitectural
FECFire extinguisher cabinetArchitectural
FFFinished floorGeneral
FFEFinished floor elevationCivil and site
FGFinished gradeCivil and site
FHFire hydrantCivil and site
FINFinishGeneral
FLFlow lineCivil and site
FRPFiberglass reinforced panelArchitectural
FRTFire-retardant treatedUsually plywood or lumberArchitectural
FSFloor sinkPlumbing and fire
FSDFire smoke damperMechanical
FTGFootingStructural
FVField verifyGeneral
GAGaugeMetal stud and sheet metal thicknessArchitectural
GALVGalvanizedArchitectural
GBGrade beamStructural
GCGeneral contractorGeneral
GFCI or GFIGround-fault circuit interrupterElectrical
GIGrease interceptorPlumbing and fire
GLB or GLULAMGlued laminated timberStructural
GND or GGroundElectrical
GPMGallons per minutePlumbing and fire
GWB or GYP BDGypsum wallboardDrywallArchitectural
HBHose bibbPlumbing and fire
HCHollow core or handicappedRead it from context: doors or accessibilityArchitectural
HDPEHigh-density polyethylene pipeCivil and site
HMHollow metalSteel doors and framesArchitectural
HMAHot mix asphaltCivil and site
HSSHollow structural sectionSteel tube or pipe sectionStructural
HT or HGTHeightGeneral
HW / HWRHot water / hot water recirculationPlumbing and fire
HWS / HWRHeating hot water supply / returnMechanical
IGIsolated groundElectrical
INSULInsulationArchitectural
INTInteriorArchitectural
INV or IEInvert elevationInside bottom of a pipe; sets trench depthCivil and site
J or JBJunction boxElectrical
JANJanitorArchitectural
JSTJoistStructural
KSIKips per square inchStructural
KVAKilovolt-ampereElectrical
KWKilowattElectrical
LSteel angleAs in L4x4x3/8Structural
LAMLaminate or laminatedArchitectural
LAVLavatoryPlumbing and fire
LLLive loadStructural
LLH / LLVLong leg horizontal / long leg verticalStructural
LPLighting panelElectrical
LVLLaminated veneer lumberStructural
LVTLuxury vinyl tileArchitectural
MAUMakeup air unitMechanical
MAXMaximumGeneral
MBMachine boltStructural
MCMetal-clad cableElectrical
MCBMain circuit breakerElectrical
MDPMain distribution panelElectrical
MFRManufacturerGeneral
MHManholeCivil and site
MINMinimumGeneral
MISCMiscellaneousGeneral
MLOMain lugs onlyElectrical
MOMasonry openingArchitectural
MSBMain switchboardElectrical
MTLMetalArchitectural
NICNot in contractShown for reference only; do not price itGeneral
NLNight lightElectrical
NTSNot to scaleDo not measure it; use the written dimensionsGeneral
O.C.On centerSpacing measured center to centerGeneral
OAOutside airMechanical
OFCIOwner furnished, contractor installedPrice the labor, not the materialGeneral
OFOIOwner furnished, owner installedGeneral
OPPOppositeGeneral
OSOccupancy sensorElectrical
PC / PTPoint of curvature / point of tangencyCivil and site
PEXCross-linked polyethylene pipePlumbing and fire
PLPlateAs in PL 1/2 x 8Structural
PLAMPlastic laminateArchitectural
PNL or PPPanel, or power panelElectrical
PRVPressure reducing valvePlumbing and fire
PSFPounds per square footGeneral
PSIPounds per square inchGeneral
PSLParallel strand lumberStructural
PTPaint, or porcelain tileOn structural sheets PT means post-tensioned or pressure-treatedArchitectural
PTPost-tensioned, or pressure-treatedConcrete slabs, or lumberStructural
PTDPaintedArchitectural
PVCPolyvinyl chloride pipePlumbing and fire
PVIPoint of vertical intersectionCivil and site
QTQuarry tileArchitectural
RAReturn airMechanical
RBRubber baseArchitectural
RCPReflected ceiling planArchitectural
RCPReinforced concrete pipeOn architectural sheets RCP is the reflected ceiling planCivil and site
RDRoof drainArchitectural
REFReferenceGeneral
REINFReinforcing or reinforcementStructural
REQDRequiredGeneral
REVRevisionGeneral
RFIRequest for informationGeneral
RGReturn grilleMechanical
RGS or GRCRigid galvanized steel conduitElectrical
RORough openingArchitectural
ROWRight of wayCivil and site
RPZReduced pressure zone backflow preventerPlumbing and fire
RTURooftop unitMechanical
SASupply airMechanical
SCSolid coreWood doorsArchitectural
SDStorm drainCivil and site
SDSmoke damper, or smoke detectorStorm drain on civil sheetsMechanical
SHShowerPlumbing and fire
SIMSimilarSame as the referenced detail, with minor differencesGeneral
SKSinkPlumbing and fire
SOGSlab on gradeStructural
SOMDSlab on metal deckStructural
SPStatic pressureMechanical
SPECSpecificationGeneral
SPRSprinklerPlumbing and fire
SQSquareGeneral
SS or SANSanitary sewerCivil and site
SSMSolid surface materialArchitectural
STAStation10+50 means 1,050 ft along the baselineCivil and site
STCSound transmission classArchitectural
STDStandardGeneral
STIFFStiffenerStructural
STLSteelArchitectural
STORStorageArchitectural
STRUCTStructuralStructural
SWBDSwitchboardElectrical
SWPPPStormwater pollution prevention planCivil and site
T/Top ofAs in T/STL, top of steelStructural
T&BTop and bottomGeneral
T&GTongue and grooveArchitectural
TBDTo be determinedGeneral
TCTop of curbCivil and site
THHNThermoplastic high heat-resistant nylon-coated wireElectrical
TOB / BOBTop of bank / bottom of bankCivil and site
TOCTop of concreteStructural
TOFTop of footingStructural
TOSTop of steel, or top of slabStructural
TOWTop of wallStructural
TPTop of pavementCivil and site
TPOThermoplastic polyolefin roofingArchitectural
TSTAT or TThermostatMechanical
TVSS or SPDSurge protective deviceElectrical
TYPTypicalApplies everywhere the same condition occurs, not just where notedGeneral
UGUndergroundElectrical
UNOUnless noted otherwiseGeneral
URUrinalPlumbing and fire
VVoltElectrical
V or VTRVent, or vent through roofPlumbing and fire
VAVVariable air volume boxMechanical
VBVapor barrierArchitectural
VCTVinyl composition tileArchitectural
VFDVariable frequency driveMechanical
VIFVerify in fieldGeneral
VRFVariable refrigerant flowMechanical
VWCVinyl wall coveringArchitectural
WWide flange steel beamW12x26: 12 in. nominal depth, 26 lb per footStructural
WWatt, or wireOn structural sheets W is a wide flange beamElectrical
W/WithGeneral
W/OWithoutGeneral
WCWater closet or wall coveringRead it from context: toilet or finishArchitectural
WCOWall cleanoutPlumbing and fire
WDWoodArchitectural
WHWater heaterPlumbing and fire
WHAWater hammer arrestorPlumbing and fire
WMWater main or water meterCivil and site
WPWaterproofingArchitectural
WPWeatherproofWaterproofing on architectural sheetsElectrical
WRBWeather-resistive barrierArchitectural
WTStructural tee cut from a W shapeStructural
WWF or WWRWelded wire fabric or reinforcementStructural
XFMR or TTransformerElectrical

Abbreviations that change what you price

Most abbreviations just save space. These change the quantity or the scope, and missing one is a common cause of a bid that is too high or too low.

Drawing abbreviations that change the takeoff or the scope, and what to do with each
Abbr.MeaningWhat it does to the estimate
NICNot in contractShown for coordination only. Leave it out of the takeoff.
FBOFurnished by othersLeave out the material; check whether you still install it.
OFCIOwner furnished, contractor installedPrice the installation labor, not the material.
ALTAlternatePrice it separately from the base bid, as the bid form asks.
EXIST / (E)ExistingNot new work, unless the notes say to remove, patch or match it.
TYPTypicalThe detail applies at every similar condition, not only where it is drawn. Count them all.
SIMSimilarSame as the referenced detail with small differences. Check the differences before copying quantities.
UNOUnless noted otherwiseThe default for the whole sheet. Find the exceptions before measuring.
EWEach wayReinforcing runs in both directions. Take off both.
EFEach faceReinforcing on both faces of a wall. Double the bars.
T&BTop and bottomTwo mats of reinforcing. Double the bars.
NTSNot to scaleNever scale it. Use the written dimensions.
VIF / FVVerify in fieldThe dimension may change. Note it as an assumption in the bid.

Abbreviations that mean different things on different sheets

The same letters are reused across disciplines. Read an abbreviation by the sheet it is on, and by its context, before you look it up.

Construction abbreviations with different meanings by discipline
Abbr.One meaningAnother meaning
EFEach face (structural)Exhaust fan (mechanical)
EAEach (general notes)Exhaust air (mechanical)
RCPReflected ceiling plan (architectural)Reinforced concrete pipe (civil)
PTPost-tensioned or pressure-treated (structural)Paint or porcelain tile (finish schedules)
SDStorm drain (civil)Smoke damper or smoke detector (mechanical)
CBCatch basin (civil)Circuit breaker (electrical)
WPWaterproofing (architectural)Weatherproof (electrical)
WWide flange beam (structural)Watt or wire (electrical)
WCWater closet (plumbing)Wall covering (finishes)
FDFloor drain (plumbing)Fire damper (mechanical)
ACAsphalt concrete (civil)Air conditioning (mechanical)
TOSTop of steelTop of slab

How to read callouts that combine abbreviations

Abbreviations are usually strung together in a callout. These are read left to right:

Examples of construction drawing callouts and how to read them
CalloutReads as
#5 @ 12" O.C. EW T&BNumber 5 rebar, 12 inches on center, each way, top and bottom: four layers of bars
T/FTG EL. 96'-0"Top of footing at elevation 96 feet 0 inches
W12x26Wide flange beam, 12 inches nominal depth, 26 pounds per foot
L4x4x3/8 LLVSteel angle, 4 by 4 inches, 3/8 inch thick, long leg vertical
5/8" TYPE X GWB EA SIDE5/8 inch fire-rated gypsum wallboard on each side of the stud
+42" AFFMounted 42 inches above finished floor
STA 10+501,050 feet along the baseline from station 0+00
8" PVC SS @ 1.0% INV 92.458 inch PVC sanitary sewer at 1 percent slope, invert elevation 92.45 feet

Bar sizes, weights and lap lengths for callouts like the first one are in the rebar sizes and weight chart.

Where to find a drawing set's abbreviation legend

Every set defines its own abbreviations, and firms differ, so the legend in the set wins over any list, including this one. Under the US National CAD Standard, sheet numbers start with a discipline letter, and the legend is usually on the first sheet of the G or A series:

Discipline letters at the start of construction drawing sheet numbers
LetterDisciplineLetterDiscipline
GGeneral: cover, index, abbreviations, symbolsAArchitectural
CCivilIInteriors
LLandscapeQEquipment
SStructuralFFire protection
PPlumbingMMechanical
EElectricalTTelecommunications

Specification sections also define terms, usually in Division 01. When the drawings and the specification disagree, the contract decides which governs, and the question belongs in an RFI before bid day. To find which division a material falls under, see the CSI divisions list.

Getting the whole set taken off

Our estimators read full drawing sets every day, notes, legends and schedules included, and deliver marked-up plans with an editable Excel workbook, usually in 24 to 48 hours. See how to read a construction estimate, how we estimate, or send the drawings for a free quote.

Common questions

Typical. The detail or dimension applies at every location with the same condition, not only where it is drawn, so count every occurrence in the takeoff.

Unless noted otherwise. It sets the default for the sheet; any location with a different note is the exception.

U.N.O., UNO and UON all mean unless noted otherwise. A note such as "5/8" gypsum board U.N.O." means every wall gets 5/8" board except the ones the drawings call out differently, so the estimator counts the exceptions first and prices the rest at the default.

Above finished floor. Mounting heights of outlets, switches, fixtures and accessories are given in inches AFF.

Not in contract. The item is shown for coordination only and is not part of the work being bid, so leave it out of the takeoff.

Owner furnished, contractor installed. The owner buys the item and the contractor installs it, so price the labor but not the material. OFOI means owner furnished, owner installed.

EW is each way: reinforcing in both directions. EF is each face: reinforcing on both faces of a wall. Both double the bars to take off.

Top of wall, usually followed by an elevation. Similar callouts are TOF (top of footing), TOC (top of concrete), TOS (top of steel or slab) and BOF (bottom of footing).

Similar. The location is built like the referenced detail with minor differences, which should be checked before copying its quantities.

On architectural sheets, reflected ceiling plan. On civil sheets, reinforced concrete pipe.

In the abbreviation legend, usually on the first general (G) or architectural (A) sheet, and sometimes on the first sheet of each discipline. The set's own legend overrides any general list.

Sources

Send your plans, get an exact price

Free quote in about 20 minutes. Estimates typically in 24 to 48 hours, with free revisions.